HomeCommunity NewsBradenton BeachRocks beat out concrete...

Rocks beat out concrete in shoreline project

BRADENTON BEACH – City officials have made significant changes to the plans for a shoreline resiliency project along Bay Drive South from the south side of the Bradenton Beach Pier to Fifth Street South.

The revised plans no longer call for a concrete resiliency wall and now propose using riprap barriers made of rocks and sand instead. The revised plans also eliminate the proposed installation of reef balls in Sarasota Bay across the street from the Old Bridge Village condominiums.

The project is being designed and engineered by the Tampa-based Environmental Science Associates (ESA) firm, with senior scientist Brett Solomon and engineer Bryan Flynn working closely with city officials.

Shoreline project no longer includes concrete wall
The proposed project area includes the Bradenton Beach Pier and the Bridge Tender Inn shoreline. – ESA | Submitted

In an effort to address king tides, rising tides and future sea level rise, the Bradenton Beach City Commission and the Bradenton Beach Community Redevelopment Agency (CRA) are jointly pursuing the resiliency project that city attorney and CRA liaison Ricinda Perry says has evolved into a shoreline renourishment project.

ESA presented the 30% completed plans in early January. In late January, Solomon and Flynn conducted publicly noticed on-site meetings with city officials and potentially impacted property owners.

During the March 17 joint city commission/CRA meeting, Solomon and Flynn presented the 60% completed plans that included revisions based on input received from city officials and potentially impacted property owners.

Wall removed

The 30% completed plans proposed installing a concrete wall and/or earthen berm along the Bay Drive South shoreline. That concept was met with much resistance from city officials and potentially impacted property owners.

Throughout the engineering process, city commissioner and CRA Chair Ralph Cole has expressed his desire for a shoreline project that uses natural materials as much as possible.

“We don’t want the wall. That’s pretty much what everybody’s decided. They don’t want a concrete barrier,” Cole said during the March 17 meeting.

The 60% completed plans approved by the city commission and CRA members that day no longer include a concrete wall.

Riprap

There’s already an existing riprap barrier about 2.5 feet high along the length of Fred Bartizal’s Bridge Tender Inn & Dockside Bar property. The revised plans propose extending the existing riprap 10 feet to the east and possibly raising it by another 1.5 feet to get to the 4-foot elevation recommended by ESA.

According to Perry, the proposed project would result in the extended Bridge Tender Inn shoreline having a beach-like appearance, with the rocks being covered by sand. Trees, mangroves and other erosion-controlling plants might also be placed in the expanded shoreline area.

Shoreline project no longer includes concrete wall
The coral-colored line indicates the location of the proposed riprap barrier. – ESA | Submitted

Matching riprap and a similarly extended shoreline would continue south to the small city-owned pocket park at the east end of Third Street South.

To accommodate the existing mangroves near the pocket park, a slightly elevated walkway would be installed between the landward side of the mangroves and the edge of Bay Drive South, with riprap placed under the walkway and along the mangroves and existing vegetation that already help absorb and dissipate wave energy. The existing mangroves will not be removed.

Shoreline project no longer includes concrete wall
The engineering plans propose a slightly elevated walkway alongside Bay Drive South. – Joe Hendricks | Sun

The walkway built over the riprap would continue south along Bay Drive South to Fifth Street South and Perry said Bartizal is amenable to the walkway continuing north on his property to Bridge Street.

Shoreline project no longer includes concrete wall
The riprap (illustrated in coral) and the elevated walkway (illustrated in yellow) would extend to Fifth Street South. – ESA | Submitted

“People won’t see the rocks,” Perry said of the riprap.

The revised plans propose small stairways or ramps that go up and over the riprap to provide uninterrupted access to the privately-owned docks along Bay Drive South.

Flynn said the riprap barriers could be raised in 10-15 years by adding more rocks and sand if conditions warrant doing so.

Reef balls

The 30% completed plans proposed installing reef balls in the bay across the street from the Old Bridge Village condominiums. The reef balls were proposed to dissipate incoming wave energy and reduce the amount of sand and sediment that washes away from the shoreline. Some condo owners expressed concern about aesthetics and visibility.

Shoreline project no longer includes concrete wall
In late January, Old Bridge Village condo owners used this prop to express their concerns about the anticipated size and visual impact of the proposed reef balls. – Joe Hendricks | Sun

The revised 60% completed plans now propose installing reef balls only along the south side of the Bridge Street Pier and clock tower walkway. Reef balls would not be placed near the condos.

Shoreline project no longer includes concrete wall
The blue circles indicate where reef balls would be placed near the Bradenton Beach Pier. – ESA | Submitted

Made of oyster shells, smaller oyster bags and oyster pyramids would be placed in the water throughout the project area to help dissipate wave energy and reduce sediment washout.

Public input

During public input at the recent joint meeting, Bartizal and residential property owners Krista Czajkowski and Marvin Taake expressed support for the revised plans.

Czajkowski said her biggest concern was maintaining the ability to install or replace boat lifts and docks. Flynn said the riprap barrier would not negatively impact boat lifts, docks or navigation.

Taake said drainage and flooding were his biggest concerns. Flynn said the proposed project will include drainage elements that improve the flow of rainwater to the outfalls that discharge into the bay.

“I think it’s win-win for everybody,” Bartizal said.

Funding

The design and engineering phase is being funded with a $92,433 resiliency grant from the Florida Department of Environmental Protection (FDEP). For state and federal permitting purposes, the design and engineering must be 100% completed in August.

The current grant does not include funds to construct the engineered project and no cost estimates to construct the proposed project have been provided. During the joint meeting, ESA and Perry were authorized to work together to pursue additional FDEP resiliency grants to construct the fully engineered and shovel-ready project. There is currently no estimated timeline as to when the proposed project would be constructed.

Most Popular

More from Author

New book highlights Drift In’s past, present, future

BRADENTON BEACH – Casey Hoffman and Paul “Big Sexy” Weremecki have...

Ferry service to Longboat Key discussed

LONGBOAT KEY – Gulf Islands Ferry service may one day be...

Hunters Point prevails in dock permitting appeal

CORTEZ – Hunters Point developer Marshall Gobuty and his Cortez Road...

Anna Maria considers regulating mangroves

ANNA MARIA – Building Depart­ment General Manager Dean Jones is leading...

Moss Builders wins mid-season tourney

ANNA MARIA – Youth soccer on the Island goes into the month of May with playoff games on the horizon. In the 8- to 10-year-old league, The Intuitive Foundation team is holding on to the first-place position over team Solid Rock Construction. With their one-point win against Isola...

Boomers continue to boom

Just when you think they’re too old to influence the smart, better-educated and computer-savvy younger generations, they raise their grey and balding heads again to remind their kids and grandkids they are still alive and influential. For years, the prediction would be that boomers would start to sell...

Police chief says crime is down in Bradenton Beach

BRADENTON BEACH – Crime is down in Bradenton Beach. “Last year I stood up here and I told you crime couldn’t go any lower in the city of Bradenton Beach, but our overall crime went down 43.5% from last year,” Police Chief John Cosby said during his annual...

Egmont, Passage keys prove enchanting

Extending approximately 5 miles from Anna Maria Island to St. Petersburg, the mouth of Tampa Bay is fronted by the barrier islands of Egmont Key and Passage Key. The surrounding waters are beautiful, ecologically important and provide anglers with some excellent fishing opportunities. The history surrounding the...

Island Players produce thrilling ‘Woman in Black’

ANNA MARIA - Anyone who regularly attends performances by the Island Players is used to lighthearted comedies that have the audience in hysterics for a great deal of the time they are in their seats. With performances of “Later Life,” “Farce of Nature,” “The Mousetrap” and “Communicating Doors,”...

County pushes for fire district mergers

MANATEE COUNTY – County commissioners asked the county’s seven fire chiefs to consider merging their districts at an April 23 meeting. Commissioners said they would support doing a study to look into the benefits of consolidating fire districts, adding that they would bring state leaders and the Office...

Jewfish Key could become part of county

MANATEE COUNTY – County commissioners and officials from the Town of Longboat Key discussed a petition from the Jewfish Key Preservation Association to de-annex Jewfish Key from the town at a joint April 30 meeting. If the de-annexation is successful, Jewfish Key will become part of unincorporated Manatee...

Irrigation system to be installed on Bridge Street

BRADENTON BEACH – The 80 newly-planted palm trees on Bridge Street will need a regular watering schedule, and on May 2, the Community Redevelopment Agency (CRA) unanimously approved the expenditure of up to $7,500 to have an irrigation system installed along both sides of the road. CRA members...

Woodard leaving Bradenton Beach

BRADENTON BEACH – With the city officially announcing the resignation of Public Works Director Tom Woodard at a May 2 commission meeting, it was also announced that Police Chief John Cosby will fill in as interim department head during the search for Woodard’s replacement. Woodard, who has been...

Longboat Key officials suggest traffic flow options for Coquina Beach

LONGBOAT KEY – Citing a study concluding that the 1.7-mile stretch of Gulf Drive from the Longboat Pass Bridge to Cortez Road is one of the most unpredictable in the region in terms of traffic expectations, Longboat Key Public Works Director Isaac Brownman asked the county to...

City may charge commercial boats to use dock

BRADENTON BEACH – The free dockage for commercial vessels at city docks may soon come at a cost. A discussion of the $5,000 cost to replace several floats lost on the floating docks during high surf in April turned to the city’s overall cost of dock maintenance and...

New book highlights Drift In’s past, present, future

BRADENTON BEACH – Casey Hoffman and Paul “Big Sexy” Weremecki have written a book about the Drift In bar. Published in March, the 144-page book is aptly titled, “Drift In, Stumble Out” and tells the tale of one of Florida’s great dive bars. Chapter 1 opens with the following...