UPDATED May 10, 2022 – ANNA MARIA – A silt fence has been erected on the undeveloped beachfront property at 105 Elm Ave., reigniting interest in an ongoing permitting process.

Bradenton resident Fedora Campbell owns the beachfront property at 105 Elm Ave. Permitting records obtained from the city of Anna Maria list Greg Gagne as the permit applicant and the Anna Maria-based Gagne Construction firm as Campbell’s contracted construction company.

The recent appearance of the silt fence does not mean the proposed construction has been fully permitted by the city and the city commission. Elm Avenue does not currently extend to Campbell’s property. Elm Avenue currently ends near the driveway for the home at 107 Elm owned by Wendy and Robert Jordan.

A city-issued right of way permit would be required for the construction company to install an unpaved, shell-covered extension of Elm Avenue in the city right of way which would then provide access to the 105 Elm driveway. The city-owned right of way at the west end of Elm Avenue also serves as a beach access entrance. On April 20, the Anna Maria Building Department received a right of way access plan from Gagne Construction.

Permitting efforts continue for 105 Elm Avenue
The unpaved portion of Elm Avenue currently ends near the Jordan’s driveway and the beach access entrance. – Joe Hendricks | Sun

On May 1, The Sun asked Anna Maria Mayor Dan Murphy about the recent installation of the silt fence.

“No vote has taken place regarding the use of the city-owned right of way. A permit to build the house has been submitted and is pending review. Meanwhile, before a permit can be reviewed, the property needs to submit soil bore samples for analysis. A silt fence is required to do the soil bore. Hence, a silt fence is up at the property,” Murphy said.

“No permits have been issued. As it stands now, no permit will be issued until the right of way issue is run by the Planning and Zoning Board for comment and then taken to the city commission and either approved or rejected. If the commission approves the right-of-way permit, then the Florida Department of Environmental Protection must also review and either reject or approve the permit request. If all approve, then a permit can be issued,” Murphy said.

Driveway access

According to Section 114-421 of the city code of ordinances, “Generally, with the exception of the planting of grass or 250 filter mix, no encumbrances of any kind, such as trees, bushes, rocks, stones, plantings, pea gravel, crushed shell, etc., shall be placed or constructed on the right-of-way within 8 feet of the edge of pavement without the written approval of the director of public works and a majority of the members of the city commission.”

Permitting efforts continue for 105 Elm Avenue
Building Director George McKay issued this right of way permit for 107 Elm Ave. in 2007. – City of Anna Maria | Submitted

On Nov. 14, 2007, then-Public Works Director George McKay approved a right-of-way work permit related to the construction of a home at 107 Elm. That permit references an “extension of driveway.” An accompanying document dated Nov. 21, 2006, references a “road extension in right of way” and noted the materials used to extend Elm Avenue to provide access to 107 Elm were to consist of #250 sand mix, FDOT screenings mix or filter mix. That permit resulted in Elm Avenue being extended without the use of asphalt or concrete. McKay’s administrative issuance of the 2007 right of way permit was not presented to the city commission for approval.

Permitting efforts continue for 105 Elm Avenue
The site plan for 105 Elm proposes a driveway that connects to an unpaved extension of Elm Avenue. – City of Anna Maria | Submitted

The need for a city commission-approved right-of-way permit was the subject of a memo that Campbell’s attorney, Kevin Hennessey, sent to the Anna Maria Building Department on April 20. Hennessey’s memo prompted a written legal opinion in the form of a memo from Anna Maria City Attorney Becky Vose, which she sent to Murphy and Hennessey on April 26.

In his memo, Hennessey cited Section 114-604 of the city code of ordinances which states, “The director of public works is authorized to approve an application/permit for right of way utilization which is in compliance with this article. After approval of an application/permit by the director of public works and payment of the required fee by the applicant, a copy of the approved application/permit will be issued to the applicant.”

Hennessy’s memo stated, “It is our position that the city code allows for administrative approval, by city staff, of the proposed right of way improvements, without the need for approval by the planning and zoning board or the city commission.”

Hennessey’s memo stated, “It is also the experience of Gagne Construction that the city has never previously made it a requirement to go in front of the city commission or planning and zoning board to get approval of a similar access/driveway work in a city right of way. The city’s public records also show that the driveway approval for the 107 Elm Ave. home, which similarly was in the Elm Avenue right of way, did not require city commission approval. The owner of 107 Elm Ave. did go before the city commission for a setback variance, but nothing in the agenda or minutes reflect any discussion of the right of way permit. Mr. Gagne also called Mr. Whitehead, who was part of the permit process for the 107 Elm Ave. property. Mr. Whitehead said the city commission meeting was not a part of the requirement for the right of way permit.”

Permitting efforts continue for 105 Elm Avenue
A city-issued right of way permit has been requested for the use of the city-owned right of way that also serves as a beach access point at the west end of Elm Avenue. – Joe Hendricks | Sun

In her memo, Vose stated, “Mr. Hennessey concludes that an administrative approval of his application is necessarily justified. I disagree with Mr. Hennessy. The authority of the director of public works to approve an application/permit for right of way utilization is limited to instances when such utilization ‘is in compliance with this article (Section 114-601).’ The section really begs the question of whether the application/permit should be granted.”

In 2017, Murphy restructured the city’s building, planning and code enforcement departments and reassigned McKay to serve as the city’s building department coordinator. Murphy assigned Dean Jones to serve as public works manager, a title Jones still holds. McKay is now an hourly employee in the city’s building department.

In her memo, Vose stated, “It should be noted that the position of director of public works is currently a vacant position. In the absence of a director of public works, the authority that would be vested in such director is actually exercised, if at all, by the mayor. Even if there were currently a director of public works, the provision that ‘the director of public works is authorized to approve an application/permit for right of way utilization which his compliance with this article’ does not mandate that the director of public works necessarily take such action, particularly due to the provisions of Section 114-421, requiring the approval of both the director of public works and a majority of the members of the city commission under certain circumstances with appear to apply here.

“In this instance, due to the possible far-reaching effects of this decision, the public scrutiny relating to this subject and the provisions of Section 114-421, the mayor, acting in the stead of the director of public works, has chosen not to make this decision himself, but rather refer it to the city commission to make that decision,” Vose stated in her memo.

“It is my opinion, that under current conditions, the city commission does have the authority to make the decision as to the approval or denial of the application for right of way permit. It is my understanding that the city will schedule your application to be heard before the planning and zoning board for a recommendation, then schedule your application to be heard before the city commission for final decision,” Vose stated in her memo.

The 105 Elm Ave. right of way use permit is scheduled for discussion at the Monday, May 16, planning and zoning board meeting at City Hall at 2 p.m. The meeting will be open to the public.

Regarding the right of way permit approval process, Murphy said, “As our city attorney interpreted the code, the director of public works only has authority over 8 feet of the right of way in front of a residence. In this case, we’re looking at approximately 70 feet of right of way and the right of way is public property and the city is the guardian of that public property. Hence, that’s the reason an employee cannot give away public property for public use. That’s a matter for the commission to decide.”

Coastal construction concerns

Through their North Carolina-based WAJ Rustic Vacations LLC, the Jordans bought the beachfront home and property at 107 Elm for $4 million on April 1, 2021. On April 23, the Jordans then bought the undeveloped 103 Elm property from Steven Decker for $500,000. The 103 Elm property is located seaward and west of Campbell’s property.

On July 6, 2021, Wendy Jordan sent Murphy an email that referenced the Jordans’ efforts to also purchase the 105 Elm property.

“We first offered the lot owner $2 million dollars for her lot; she is 83 years old. She asked for $2 million and we met to set the closing and then she turned it down,” Jordan stated in her email.

In that email, she also stated, “For those who immediately say, ‘You are only worried about your view.’ Of course I am worried about my view. We paid for a view and it is in jeopardy of change that will ruin the wildlife.”

Permitting efforts continue for 105 Elm Avenue
Wendy and Robert Jordan’s beachfront home at 107 Elm Ave. currently has a mostly unobstructed view of the beach and the Gulf of Mexico. – Joe Hendricks | Sun

The Jordans have publicly opposed the construction of a new home at 105 Elm through the Preserve AMI website and public awareness campaign they launched a few months after purchasing their new home. According to the Preserve AMI website, the Jordans and some of the other Preserve AMI supporters are also concerned that allowing Campbell’s home to be built seaward and west of the state of Florida’s Coastal Construction Control Line (CCCL) would establish a precedent regarding the development of other undeveloped properties seaward of the Coastal Construction Control Line.

On June 25, 2020, the Florida Department of Environmental Protection provided Campbell with a notice to proceed and a permit for her desired construction activities at 105 Elm Ave.

On Aug. 3, 2020, attorney David Levin filed a petition for a formal administrative hearing with the Florida Department of Administrative Hearings (DOAH). Levin filed that petition on behalf of potentially impacted property owners David Morris, Ling Liu, DAR Real Estate Enterprises and Richard Theidel. The Jordans did not own the 107 Elm property at that time.

“Campbell’s proposed structures do not comply with the applicable requirements and are not eligible for a CCCL permit. Petitioners seek a final order revoking Permit No. ME-1341,” Levin stated in his petition.

In response to that request, administrative law judge Francine Ffolkes later presided over a six-day DOAH hearing. On June 7, 2021, Ffolkes issued her written recommended order which stated: “It is hereby recommended that DEP enter a final order granting Campbell’s application for a CCCL permit to construct a single-family residence and associated structures seaward of the CCCL.”

Permitting efforts continue for 105 Elm Avenue
These plans illustrate what the proposed residential structure at 105 Elm would look like. – City of Anna Maria | Submitted

On July 20, 2021, Interim FDEP Secretary Shawn Hamilton signed the final order that formalized Ffolkes’ recommended order. The final order provided a 30-day appeal period. On Aug. 12, 2021, the Jordans filed three notices of appeal regarding Hamilton’s final order, but at the advice of Levin, they later decided to stop their appeal process.

Related coverage:

 

Building permit sought for beachfront property

 

Impact of FDEP permitting order remains to be seen

 

FDEP allows beachfront development

 

Beachfront homeowners launch Preserve AMI campaign

Most Popular

More from Author

Local designer featured at Bealls Florida

BRADENTON – Kelly Hunt grew up on Anna Maria Island and...

Farrington resigns, seeks supervisor of elections job

MANATEE COUNTY – County voters will ultimately determine whether former Chief...

Reimagining Pine Avenue bid higher than expected

ANNA MARIA – Mayor Dan Murphy is among those disappointed with...

Commission receives proposed charter amendments

ANNA MARIA – Six potential charter amendments and an ad­ditional recommendation...

TDC considers adding third ferry boat

BRADENTON - The Manatee County Tourist Development Council (TDC) discussed the status of the new water ferry service and the possibility of adding a third ferry on April 15. The Gulf Islands Ferry service began in January with two boats stopping at the Bradenton Beach Pier, the Anna...

TDC recommends raising tourist tax

BRADENTON - A visit to Manatee County could soon cost tourists more, as the Manatee County Tourist Development Council (TDC) voted unanimously to recommend raising the county’s tourism tax from 5% to 6% at its April 15 meeting. The TDC makes recommendations to the Manatee County Commission, which...

Tourism numbers rise

ANNA MARIA - Research Data Services’ Anne Wittine presented her upbeat state of tourism report to the Manatee County Tourist Development Council (TDC) on April 15. Wittine’s report featured the latest available statistics related to the tourism industry in Manatee County from February 2024 compared to February 2023. Total...

Mayors propose to regulate mangroves

LONGBOAT KEY – The mayors of the three Anna Maria Island cities and Longboat Key are considering making a joint application to the Florida Department of Environmental Protection (FDEP) to obtain local control over mangrove regulations. The discussion took place at the Coalition of Barrier Island Elected Officials...

Officials discuss state plan to replace Longboat Pass Bridge

LONGBOAT KEY – Members of the Coalition of Barrier Island Elected Officials (BIEO) discussed the proposed new Longboat Pass Bridge on April 17. The Florida Department of Transportation (FDOT) District One has initiated a project development and environment study for SR 789 (Gulf Drive/Gulf of Mexico Drive) from...

Marina bar remains closed

BRADENTON BEACH – After city officials put a halt to what they said was the unpermitted operation of a new bar at the Bradenton Beach Marina in March, building official Darin Cushing said the proper approval process is now underway. On March 25, the Marina Facebook page announced...

Local designer featured at Bealls Florida

BRADENTON – Kelly Hunt grew up on Anna Maria Island and her Island-inspired creative designs appear on a line of beach towels now sold at 68 Bealls Florida stores statewide. Hunt now lives in Bradenton with her husband, Courtland, and their son Kellan, and her parents, Scott and...

Tarpon primer: Part One

Tarpon season is one of the most anticipated times of the year in local waters. While I’ve encountered tarpon occasionally most every month of the year, April through July is the time ardent anglers turn their sights to these beautiful fish. Their arrival in numbers worth pursuing...

Anna Maria Island community remembers philanthropist

ANNA MARIA ISLAND – Charles “Chuck” Lester’s legacy of philanthropy and friendship is being remembered on Anna Maria Island following his passing on April 19 at the age of 92. “I have nothing but great feelings for Chuck. I have such admiration and respect for a life well-lived,”...

Farrington resigns, seeks supervisor of elections job

MANATEE COUNTY – County voters will ultimately determine whether former Chief of Staff Scott Farrington or recent gubernatorial appointee James Satcher serves as Manatee County’s next supervisor of elections. Farrington and Satcher are expected to square off in the Republican primary election that concludes on Aug. 20. If no...

Three crashes damage two businesses, one crosswalk signal

HOLMES BEACH – Two cars drove into two neighboring businesses on two separate days last week, followed by a crash into a crosswalk signal and pedestrian barrier at the nearby intersection of Marina and Gulf drives. Six people were injured in the accidents, none reported as critical. The first...

Intuitive Foundation team gives it their all

ANNA MARIA – Three games into the 8- to 10-year-old youth soccer league at The Center, team Solid Rock Construction is undefeated with three wins. Meanwhile, the Shady Lady Horticultural Services team comes close each week but still looks for their first victory. Just under the Solid Rock...