Mayor provides pier construction update

ANNA MARIA – On Friday afternoon, Mayor Dan Murphy provided Manatee County Senior Administrative Specialist Monica Luff with an update on the construction of the new Anna Maria City Pier being built by i+iconSoutheast.

The construction update was requested by Luff, who works with the Bradenton Area Convention and Visitors Bureau and the Tourist Development Council. Both governmental entities answer to Manatee County’s Board of County Commissioners.

According to Murphy, the pier project’s total anticipated cost is approximately $4.8 million. In 2018, the county commission committed $1.5 million to the project using funds generated by the county’s 5 percent tourist tax. The county commission also allocated an additional $330,000 in surplus beach concession revenues for the project. The county’s funding commitments equate to approximately 37 percent of the total anticipated project costs.

In his Friday, Feb. 22, update to Luff, Murphy wrote, “The status of the Anna Maria City Pier project is as follows:

  • We are in the pile driving phase of construction.
  • As of today, all 70 piles for the T-end of the pier have been driven. The T-end supports both the restaurant and bait shop;
  • The T-end piles are 50’ long by 14” in diameter, each weighing 5,000 lbs.;
  • There are approximately 134 more pilings to go for the walkway leading out to the pier;
  • On average, seven piles are driven each day. Weather permitting, the contractor works six days per week;
  • All piles and equipment are transported by barge from St. Pete. and/or Tampa to Anna Maria so as to alleviate traffic congestion on the Island;
  • The barge will leave Anna Maria this Monday to procure more equipment and piles, returning Thursday (2/28), weather permitting;
  • Next phase will be placing the concrete pre-cast slabs on top of the T-end pilings, building bents (deck supports) for the walk-way out and installing utilities to the pier T-end;
  • In spite of several foul weather days, the project remains on track for platform completion by August 28, 2019,” Murphy wrote.

The construction of the pier buildings will be addressed in a yet-to-be-issued request for proposals (RFP). The selected firm will then begin a subsequent and possibly congruent phase of construction once the T-end platform is completed. It is not yet known when that RFP will be issued or when that construction phase will begin and end. Murphy said previously he expects the pier to be opened to the public by year’s end.

The forthcoming RFP process is partially contingent on the negotiations between Murphy and current pier tenant Mario Schoenfelder regarding the tenant’s contributions to the project.

Murphy has suggested Schoenfelder contribute $500,000 toward the interior buildout of the restaurant and bait shop spaces. In exchange, Schoenfelder would be allowed to provide some input on the interior design and interior components. Schoenfelder’s current lease expires in December 2020.

Mayor provides pier construction update
Due to high winds and choppy seas, no pier construction work took place on Wednesday, Feb. 13. – Joe Hendricks | Sun

On Feb. 14, Murphy provided the city commission with its first update since the construction started. He said the i+iconSoutheast crew lost two days of work that week due to inclement weather and choppy seas. Murphy said the construction company feared for the safety of its employees because of the waves created by the windy conditions. A visit to the pier worksite the previous day indicated no work taking place that day.

Most Popular

More from Author

Local designer featured at Bealls Florida

BRADENTON – Kelly Hunt grew up on Anna Maria Island and...

Farrington resigns, seeks supervisor of elections job

MANATEE COUNTY – County voters will ultimately determine whether former Chief...

Reimagining Pine Avenue bid higher than expected

ANNA MARIA – Mayor Dan Murphy is among those disappointed with...

Commission receives proposed charter amendments

ANNA MARIA – Six potential charter amendments and an ad­ditional recommendation...

TDC considers adding third ferry boat

BRADENTON - The Manatee County Tourist Development Council (TDC) discussed the status of the new water ferry service and the possibility of adding a third ferry on April 15. The Gulf Islands Ferry service began in January with two boats stopping at the Bradenton Beach Pier, the Anna...

TDC recommends raising tourist tax

BRADENTON - A visit to Manatee County could soon cost tourists more, as the Manatee County Tourist Development Council (TDC) voted unanimously to recommend raising the county’s tourism tax from 5% to 6% at its April 15 meeting. The TDC makes recommendations to the Manatee County Commission, which...

Tourism numbers rise

ANNA MARIA - Research Data Services’ Anne Wittine presented her upbeat state of tourism report to the Manatee County Tourist Development Council (TDC) on April 15. Wittine’s report featured the latest available statistics related to the tourism industry in Manatee County from February 2024 compared to February 2023. Total...

Mayors propose to regulate mangroves

LONGBOAT KEY – The mayors of the three Anna Maria Island cities and Longboat Key are considering making a joint application to the Florida Department of Environmental Protection (FDEP) to obtain local control over mangrove regulations. The discussion took place at the Coalition of Barrier Island Elected Officials...

Officials discuss state plan to replace Longboat Pass Bridge

LONGBOAT KEY – Members of the Coalition of Barrier Island Elected Officials (BIEO) discussed the proposed new Longboat Pass Bridge on April 17. The Florida Department of Transportation (FDOT) District One has initiated a project development and environment study for SR 789 (Gulf Drive/Gulf of Mexico Drive) from...

Marina bar remains closed

BRADENTON BEACH – After city officials put a halt to what they said was the unpermitted operation of a new bar at the Bradenton Beach Marina in March, building official Darin Cushing said the proper approval process is now underway. On March 25, the Marina Facebook page announced...

Local designer featured at Bealls Florida

BRADENTON – Kelly Hunt grew up on Anna Maria Island and her Island-inspired creative designs appear on a line of beach towels now sold at 68 Bealls Florida stores statewide. Hunt now lives in Bradenton with her husband, Courtland, and their son Kellan, and her parents, Scott and...

Tarpon primer: Part One

Tarpon season is one of the most anticipated times of the year in local waters. While I’ve encountered tarpon occasionally most every month of the year, April through July is the time ardent anglers turn their sights to these beautiful fish. Their arrival in numbers worth pursuing...

Anna Maria Island community remembers philanthropist

ANNA MARIA ISLAND – Charles “Chuck” Lester’s legacy of philanthropy and friendship is being remembered on Anna Maria Island following his passing on April 19 at the age of 92. “I have nothing but great feelings for Chuck. I have such admiration and respect for a life well-lived,”...

Farrington resigns, seeks supervisor of elections job

MANATEE COUNTY – County voters will ultimately determine whether former Chief of Staff Scott Farrington or recent gubernatorial appointee James Satcher serves as Manatee County’s next supervisor of elections. Farrington and Satcher are expected to square off in the Republican primary election that concludes on Aug. 20. If no...

Three crashes damage two businesses, one crosswalk signal

HOLMES BEACH – Two cars drove into two neighboring businesses on two separate days last week, followed by a crash into a crosswalk signal and pedestrian barrier at the nearby intersection of Marina and Gulf drives. Six people were injured in the accidents, none reported as critical. The first...

Intuitive Foundation team gives it their all

ANNA MARIA – Three games into the 8- to 10-year-old youth soccer league at The Center, team Solid Rock Construction is undefeated with three wins. Meanwhile, the Shady Lady Horticultural Services team comes close each week but still looks for their first victory. Just under the Solid Rock...