ANNA MARIA – The $3.33 million contract to build the decking and walkway for the new Anna Maria City Pier is a done deal.

On Thursday, Nov. 29, City Commissioners unanimously authorized Mayor Dan Murphy to execute the construction contract with Tampa-based Infrastructure & Industrial Contractors Southeast Inc. (i+icon).

The contract gives i+icon 270 days to complete the pier project by Aug. 26, 2019. It allows the city to penalize the firm $975 per day for any delays beyond that date but gives the commission the discretion to extend the construction timeline due to a storm, prolonged loss of power or some other unforeseen occurrence.

Murphy said i+icon indicated the first pier pilings will be driven in January.

The contract states the new pier will be approximately 730 feet long and 12 feet wide, with a 111-foot by 88-foot T-end section to accommodate a restaurant, bait shop and restrooms. The scope of work does not include the restaurant, bait shop and restrooms spaces that will be addressed in a separate request for proposals (RFP).

The commission-approved contract is $332,837 lower than the $3.66 million bid i+icon submitted in October as one of five firms responding to the city’s revised RFP. Those bids ranged from $4.78 million to $3.45 million, and the commission then authorized Murphy to discuss contract terms with i+icon as the highest-ranked bidder.

Anna Maria pier contract handshake
Project engineer Jay Saxena, Mayor Dan Murphy and i+icon representatives Greg Thornton and Paul enjoyed a congratulatory moment after last week’s meeting. – Joe Hendricks | Sun

I+icon Operations Manager Paul Johnson and Project Manager Greg Thornton attended last week’s meeting, as did Jay Saxena from Ayres Associates, the city’s contracted pier engineering firm.

“This document marks a major milestone for the city. A lot of people have worked very hard and long to get to this point,” Murphy said when presenting the revised bid and contract for commission approval.

Cost savings

Murphy said the city could save $180,000 by using wooden support bents for the pier decking instead of the concrete bents originally planned.

Commissioner Brian Seymour asked Saxena if wood bents would reduce the new pier’s anticipated 75-year service life. Saxena said the first 63 bents from shore would be wood. The remaining walkway and T-end bents will be concrete and provide additional support where it’s most needed. The commission supported this change.

The commission also supported Murphy’s suggestion to spend $8,863 to purchase concrete pilings that are 14-inches in diameter and already cast to the correct length, rather than spending an additional $30,000 to splice together some of the 12-inch concrete pilings the city recently purchased directly to avoid paying sales tax and to ensure availability.

Murphy said Saxena and i+icon located the longer, larger pilings in the same storage yard where the previously purchased are being stored, and the city will receive a credit for 12-inch pilings returned. Murphy and Saxena noted the 14-inch pilings would support the T-end that is more vulnerable to high winds and waves.

Murphy told the commission i+icon recommended spending an additional $50,000 for IPE wood product pier decking instead of the Kebony wood product decking the commission majority approved in March. Murphy said the IPE product has a longer history of use than the newer Kebony decking. Commissioner Carol Carter noted that Seymour favored the IPE decking in March.

The revised total bid and cost savings document discussed last week lists an additional $181,700 in savings for pilings. Murphy explained later that this is for the pilings already purchased.

“There’s more savings to be had here,” he told the commission regarding the city’s continued ability to purchase construction materials directly to avoid the sales tax.

The final contracted price is approximately $800,000 lower than the original $4.13 bid i+icon submitted in August as one of two firms responding to the original RFP.

Carter commended Murphy, Saxena and i+icon for also reducing the original projected completion date of December 2019.

Related Coverage

Anna Maria City Pier proposals still awaiting approval

Five names entered into Anna Maria City Pier bidding hat

Most Popular

More from Author

Local designer featured at Bealls Florida

BRADENTON – Kelly Hunt grew up on Anna Maria Island and...

Farrington resigns, seeks supervisor of elections job

MANATEE COUNTY – County voters will ultimately determine whether former Chief...

Reimagining Pine Avenue bid higher than expected

ANNA MARIA – Mayor Dan Murphy is among those disappointed with...

Commission receives proposed charter amendments

ANNA MARIA – Six potential charter amendments and an ad­ditional recommendation...

TDC considers adding third ferry boat

BRADENTON - The Manatee County Tourist Development Council (TDC) discussed the status of the new water ferry service and the possibility of adding a third ferry on April 15. The Gulf Islands Ferry service began in January with two boats stopping at the Bradenton Beach Pier, the Anna...

TDC recommends raising tourist tax

BRADENTON - A visit to Manatee County could soon cost tourists more, as the Manatee County Tourist Development Council (TDC) voted unanimously to recommend raising the county’s tourism tax from 5% to 6% at its April 15 meeting. The TDC makes recommendations to the Manatee County Commission, which...

Tourism numbers rise

ANNA MARIA - Research Data Services’ Anne Wittine presented her upbeat state of tourism report to the Manatee County Tourist Development Council (TDC) on April 15. Wittine’s report featured the latest available statistics related to the tourism industry in Manatee County from February 2024 compared to February 2023. Total...

Mayors propose to regulate mangroves

LONGBOAT KEY – The mayors of the three Anna Maria Island cities and Longboat Key are considering making a joint application to the Florida Department of Environmental Protection (FDEP) to obtain local control over mangrove regulations. The discussion took place at the Coalition of Barrier Island Elected Officials...

Officials discuss state plan to replace Longboat Pass Bridge

LONGBOAT KEY – Members of the Coalition of Barrier Island Elected Officials (BIEO) discussed the proposed new Longboat Pass Bridge on April 17. The Florida Department of Transportation (FDOT) District One has initiated a project development and environment study for SR 789 (Gulf Drive/Gulf of Mexico Drive) from...

Marina bar remains closed

BRADENTON BEACH – After city officials put a halt to what they said was the unpermitted operation of a new bar at the Bradenton Beach Marina in March, building official Darin Cushing said the proper approval process is now underway. On March 25, the Marina Facebook page announced...

Local designer featured at Bealls Florida

BRADENTON – Kelly Hunt grew up on Anna Maria Island and her Island-inspired creative designs appear on a line of beach towels now sold at 68 Bealls Florida stores statewide. Hunt now lives in Bradenton with her husband, Courtland, and their son Kellan, and her parents, Scott and...

Tarpon primer: Part One

Tarpon season is one of the most anticipated times of the year in local waters. While I’ve encountered tarpon occasionally most every month of the year, April through July is the time ardent anglers turn their sights to these beautiful fish. Their arrival in numbers worth pursuing...

Anna Maria Island community remembers philanthropist

ANNA MARIA ISLAND – Charles “Chuck” Lester’s legacy of philanthropy and friendship is being remembered on Anna Maria Island following his passing on April 19 at the age of 92. “I have nothing but great feelings for Chuck. I have such admiration and respect for a life well-lived,”...

Farrington resigns, seeks supervisor of elections job

MANATEE COUNTY – County voters will ultimately determine whether former Chief of Staff Scott Farrington or recent gubernatorial appointee James Satcher serves as Manatee County’s next supervisor of elections. Farrington and Satcher are expected to square off in the Republican primary election that concludes on Aug. 20. If no...

Three crashes damage two businesses, one crosswalk signal

HOLMES BEACH – Two cars drove into two neighboring businesses on two separate days last week, followed by a crash into a crosswalk signal and pedestrian barrier at the nearby intersection of Marina and Gulf drives. Six people were injured in the accidents, none reported as critical. The first...

Intuitive Foundation team gives it their all

ANNA MARIA – Three games into the 8- to 10-year-old youth soccer league at The Center, team Solid Rock Construction is undefeated with three wins. Meanwhile, the Shady Lady Horticultural Services team comes close each week but still looks for their first victory. Just under the Solid Rock...