MANATEE COUNTY – Due to delays in receiving materials, work to repair and relocate a water main along the Anna Maria Island Bridge on Manatee Avenue is being postponed until late September or October. The county will notify residents when the work will recommence and what impacts to travel it may cause.
Crews will be completing the last phase of the water main pipe repair, installing additional hangers to support the pipe on the east side of the bridge. Due to safety concerns, the work is not possible at night, so there will likely be lane closures and periods of one-way traffic on the bridge.
It is anticipated that the work to secure the pipe will take two to three weeks, according to a press release.
The main source of water to Anna Maria Island, the 16-inch aging water main pipe broke on June 19, causing intermittent drops in water pressure to Island residents. While repairs were underway, the north end of the Island received water through Bradenton Beach via a pipe from the south. The main was brought back into service the week of July 10.